S
samantha
Is the % Complete field always tied to duration of project? My PM's are
wanting %complete to represent actual work completed, not time. Is there a
way to do this? Example being that we may be 50% of the way through the
project but actual work completed may only be 35%, and this is what they want
represented. Does the actual % Complete change from day to day because you
are one day closer to the end date? Can this field be linked to something
other then start and finish date?
wanting %complete to represent actual work completed, not time. Is there a
way to do this? Example being that we may be 50% of the way through the
project but actual work completed may only be 35%, and this is what they want
represented. Does the actual % Complete change from day to day because you
are one day closer to the end date? Can this field be linked to something
other then start and finish date?