I have baselined my project, now I want to be able to compare my % complete
actual to the % complete I should be at based upon the baseline. How can I do
this in Project, or do I have to export to Excel and calculate it?
Example: Task A is 25% complete as of today. When looking at the baseline,
it should be 50% complete as of today. How do I get Project to show this?
Thanks in advance