% complete vs baseline % complete

S

Saline04

I have baselined my project, now I want to be able to compare my % complete
actual to the % complete I should be at based upon the baseline. How can I do
this in Project, or do I have to export to Excel and calculate it?


Example: Task A is 25% complete as of today. When looking at the baseline,
it should be 50% complete as of today. How do I get Project to show this?

Thanks in advance
 
R

Rod Gill

Project doesn't show a Baseline % you should be complete, but if your
resources are assigned realistically then you can used earned value to
calculate what you want. Search help for earned value, but don't bother if
your resources are not realistically assigned (100% is rarely realistic!!).
 