I have a project that has some tasks that were scheduled months in the future
but were completed early. When I view the resource usage those tasks still
show as work. The Act. Work cell also shows hours that equal Work. When you
click task info it shows the task completed.
Why is the Resource usage view showing the hours in the WORk and ACT. WORK
cells?
but were completed early. When I view the resource usage those tasks still
show as work. The Act. Work cell also shows hours that equal Work. When you
click task info it shows the task completed.
Why is the Resource usage view showing the hours in the WORk and ACT. WORK
cells?