J
jpas1954
I am setting up a schedule in Project 2003. Within it are a couple of tasks
that must start no earlier than Feb. 2, 2006. I have gone into the 'Advanced'
tab and set them that way. Perhaps there's something fundamentally flawed
about my understanding of this, but I can't see where that's reflected
anywhere in the schedule. Next to the tasks are an icon indicating the
constraint. But the start date of the tasks is the next day after the
predecessor, as if I'd never set it. And if I look at the 'To-Do' view, I
see these tasks needing to get done on the early date not the constrained
date.
I would have expected that Project would push the 'Start' date out to equal
with the Constraint date. If it doesn't do that - and it shows up in the
earlier date in reports - what good is using it? Is there some setting I have
to adjust?
that must start no earlier than Feb. 2, 2006. I have gone into the 'Advanced'
tab and set them that way. Perhaps there's something fundamentally flawed
about my understanding of this, but I can't see where that's reflected
anywhere in the schedule. Next to the tasks are an icon indicating the
constraint. But the start date of the tasks is the next day after the
predecessor, as if I'd never set it. And if I look at the 'To-Do' view, I
see these tasks needing to get done on the early date not the constrained
date.
I would have expected that Project would push the 'Start' date out to equal
with the Constraint date. If it doesn't do that - and it shows up in the
earlier date in reports - what good is using it? Is there some setting I have
to adjust?