Converting Task into milestone

S

Shash

How do I convert an existing task (which has some duration) into milestone ?
marking as milestone does not bring up the milestone symbol ?
 
J

Jack Dahlgren

Shash said:
How do I convert an existing task (which has some duration) into milestone ?
marking as milestone does not bring up the milestone symbol ?

The default gantt view should show any task marked as a milestone with the
milestone symbol. Perhaps you have a view which has modified the barstyles.
To check go to format menu, select Barstyles and add a line. Set the "show
for ... tasks" to "milestone" and have it draw from "finish" to "finish".
Then set the symbol you want to display.
 
G

Gérard Ducouret

Hello Shash,

Normally, you just have to select the box : "Mark task as milestone" in the
Advanced tab of the Task Information dialog.
May be the Milestone symbole has been deleted in the Bar Styles dialog.
Format / Bar styles...

Hope this helps,

Gérard Ducouret
 