I need to copy a main task and all sub tasks(indented under it) to a
blank new task line. What is the best way to do this? I have version 2003.

Thanks
 
J

JulieS

Hi Tim_Ver,

Select the summary task, copy and paste. The subtasks will be copied as
well.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
M

Mike Glen

Hi Tim,

Welcome to this Microsoft Project newsgroup :)

Click the minus sign next to the summary task to close down the sub-tasks.
Now click in the summary task ID cell to select it all. Now click and drag,
hoding dowm the Crtl key to get a copy. You might like to have a look at my
series on Microsoft Project in the TechTrax ezine, particularly #4 -
Manipulating Data, at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
T

Tim_Ver

I did try this I select task right click copy and the click on the new blank
task cell and paste but it just paste the text and no minus/plus sign hence
no sub tasks.

:( Arghh , Not sure why or what I am missing.
 
J

JulieS

Hi Tim,

Make sure you select the task by clicking on the row number, not just
the task name.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top