It does sound like resource leveling may be the source of your observed
behavior - is it set to "automatic?" (Tools, Leveling) I'm curious about
your assertion that all 700 sites can go in parallel, starting together
and finishing about the same date, and yet share resources. People
can't be in two places at once. How can Joe be at the New York site
waxing widgets and also at the Los Angeles site polishing fids all on
the same day? Thaty's what you're saying will happen in your
description below.
--
Steve House
MS Project MVP
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Beemer said:
Thanks all for your help. I have found out that the shift in dates has
something to do with the resources allocated to the tasks being copied
as I made a new project (A whole new file from scratch) and made tasks
with milestones that rolled up into a summary task (The black bar with
upside down arrows at the ends). That copied just fine. I select the row
that the summary task is in and copy it..when all goes well the start
date and end date stay the same proving that all the tasks contained
within are the same. When I added some example resources to the original
and copied the summay task the dates changed. Is it doing some automatic
resource leveling?
When I said 700 small projets what I mean in real life is that I have
700 sites to build, each has started on the same day and will end around
the same time. I would like to track 25 different tasks that are
necessary from leasing a site to the construction of the actual site.
So, I would like to make a few example schedules and copy them so I have
700 mini projects but perhaps the word is summary tasks. Thing is that
each one is independent of the others but they can share resources. The
end goal is to be able to predict the resources needed to complete the
700 sites in the time allotted.