B
bsky201
My company is a Construction Management/General Contractor. I have created a
cost loaded schedule that has our customer's price (which includes our cost,
fringes, overheads and profit). We are having our subcontractor update his
portion of the schedule but do not want him seeing our final cost to our
customer. How can I share a file with both a subcontractor and our customer
but not allow the subcontractor to see all of the built up cost?
cost loaded schedule that has our customer's price (which includes our cost,
fringes, overheads and profit). We are having our subcontractor update his
portion of the schedule but do not want him seeing our final cost to our
customer. How can I share a file with both a subcontractor and our customer
but not allow the subcontractor to see all of the built up cost?