I have a builder in the reource sheet his cost is £6000 for the job. which
is in the cost per use field I need to assign him to various tasks how can I
assign him and not have him record a a cost of 6000 in the project each time
I use him?
Thanks
I have a builder in the reource sheet his cost is £6000 for the job. which
is in the cost per use field I need to assign him to various tasks how can I
assign him and not have him record a a cost of 6000 in the project each time
I use him?