Costs in resource sheet

K

kim

Hi
I have a builder in the reource sheet his cost is £6000 for the job. which
is in the cost per use field I need to assign him to various tasks how can I
assign him and not have him record a a cost of 6000 in the project each time
I use him?
Thanks
 
R

Reid McTaggart

You need to learn just a little about resource rate tables. there are
of them: A, B, C, D, and E.

Very likely, your builder's 6000 per use is entered in rate table A
and the other tables are probably blank (0 rate).

Go to the Task Usage view.
Select the row for the task and the builder that you want to set t
zero
Double-click or press <Shift>-<F2>
In the Cost Rate Table drop-down, select B

Check the results in the cost field.

Best regards,
Reid McTaggart
bluebadges.com
 
K

kim

Thank you!

Reid McTaggart said:
You need to learn just a little about resource rate tables. there are 5
of them: A, B, C, D, and E.

Very likely, your builder's 6000 per use is entered in rate table A,
and the other tables are probably blank (0 rate).

Go to the Task Usage view.
Select the row for the task and the builder that you want to set to
zero
Double-click or press <Shift>-<F2>
In the Cost Rate Table drop-down, select B

Check the results in the cost field.

Best regards,
Reid McTaggart