Create Combination View MS Project 2003 pro

D

djwelch

Is it possible to create a combination view where the upper view is a
Gantt and the lower view is resource useage? But, I only want to see
the resources assigned to the highlighed task in the upper view.

Restated, the assignments of the highlighted task in the upper view,
filter which resources and which resouce tasks are shown the the lower
Resource Useage view.


Thanks, Denis
 
D

djwelch

Thanks Jan,

You're right, almost. The lower resource usage view does limit to the
associated resources assigned to the upper view selected task. However
the tasks listed below each resource, lists all the tasks that resource
is assigned to, not just the highlisted task. How can I apply a filter
to the usage view base upon the highlighted task in the upper view?

Thanks,

Denis
 
J

Jan De Messemaeker

Hi,

Seems to me that then the lower view should be the task usage view.
If that doesn't help you, bad luck :-(
 