A
Alexandro
I have created an RBS structure for my organization, so that each
manager has its own group of resources that can be allocated on its
projects. What i need now is the opportunity for the manager to check
the hours of work scheduled in each project for all the resources he
manages, before he allocate the resourse on an activity of a new
project...
I know that I can do that by using Project web access, and in fact i
created a report using the Olap cube showing this information, but the
managers of the organization want to have this kind of information in
the Project Professional.
I found that the "resource usage" view is very close to what i
need...the only problem is that the resource usage view shows the work
only for the resources allocated over the activity i selected...I would
like to see the information for all the resource the manager manages,
before he creates the team from the resource pool organization.
I tried to customize the resource usage view...but it seems to me that
i cannot add new rows in the view, but only adding new
coloumns...that's not what i need...
Is it possible, using vb code, showing into a view from Project
Professional all the
resource managed by a project manager and not only the ones allocated
on the selected activity???
That's what my managers asked me, so i don't need to know that by PWA
they can gain this kind of information...I need to know if i can give
them the informations inside the Project Professional, before a manager
create any activity of a project.
If it is possible writing vb code to do that, could you also give me a
starting point, 'cause i'm new writing vba code.
Any help will be appreciated
Thanks
Alexandro
manager has its own group of resources that can be allocated on its
projects. What i need now is the opportunity for the manager to check
the hours of work scheduled in each project for all the resources he
manages, before he allocate the resourse on an activity of a new
project...
I know that I can do that by using Project web access, and in fact i
created a report using the Olap cube showing this information, but the
managers of the organization want to have this kind of information in
the Project Professional.
I found that the "resource usage" view is very close to what i
need...the only problem is that the resource usage view shows the work
only for the resources allocated over the activity i selected...I would
like to see the information for all the resource the manager manages,
before he creates the team from the resource pool organization.
I tried to customize the resource usage view...but it seems to me that
i cannot add new rows in the view, but only adding new
coloumns...that's not what i need...
Is it possible, using vb code, showing into a view from Project
Professional all the
resource managed by a project manager and not only the ones allocated
on the selected activity???
That's what my managers asked me, so i don't need to know that by PWA
they can gain this kind of information...I need to know if i can give
them the informations inside the Project Professional, before a manager
create any activity of a project.
If it is possible writing vb code to do that, could you also give me a
starting point, 'cause i'm new writing vba code.
Any help will be appreciated
Thanks