How Can i create % plan in my project.
I want to see my % plan & % act. in 2 column in my File and make it VISUAL
in Gunt chart if its posible.
 
M

Mike Glen

Hi Ashkan,

Welcome to this Microsoft Project newsgroup :)

Project uses %Complete (calendar time related) %Work Completed (man-hours of
work related) and Physical%Complete (measuring the physical completeness of
the task). I suggest you read the Help files on their usage. Then apply a
Baseline and view the results in the Tracking Gantt view. See
http://tinyurl.com/2xbhc for Project Tutorials

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top