Hi,
I use View/Tracking Gantt to compare my Baseline vs Scheduled Dates for
progress.
However I want to compare my, for instance, Baseline5 vs Scheduled Dates.
But I dont want to do this through Format/Bar Styles where i manually change
Baseline information to Baseline5 information. I want to create a new view
where I can easily define comparing BaselineX to scheduled. It is very
cumbersome to try this through Format/Bar Styles...Any ideas?