Creating a new view with baselineX vs scheduled

M

Modern Talking

Hi,
I use View/Tracking Gantt to compare my Baseline vs Scheduled Dates for
progress.
However I want to compare my, for instance, Baseline5 vs Scheduled Dates.
But I dont want to do this through Format/Bar Styles where i manually change
Baseline information to Baseline5 information. I want to create a new view
where I can easily define comparing BaselineX to scheduled. It is very
cumbersome to try this through Format/Bar Styles...Any ideas?
 
R

Rod Gill

It's easy! Select View, More Views
Select the Tracking Gantt Chart
Click the Copy button
Name the new view Tracking Gantt 1
Scroll down the list of bars and replace all instances of Baseline with
Baseline1
Click OK, repeat for Baselines 2-10

You now have 10 views, once for each extra baseline.
 