I have a strange situation where critical path indicators and the late finish
date are both showing different values for tasks depending on which user
opens the project file.
e.g. If one User opens the project from Project Server then Task A shows the
following (I believe correctly)
Forecast Date : 02/07/08
Critical?: No
Late Finish: 12/08/08
If another User opens the project (in eother read/write or read only mode)
then the following shows. I think this has to be incorrect anyway as the the
Critical indicator would be showing Yes if the late finish date was the same
as the forecast date?
Forecast date: 02/07/08
Critical?: No
Late Finish: 02/07/08
Can anyone explain why this happens?
We're using MS Project Server & MS Project Pro 2003
date are both showing different values for tasks depending on which user
opens the project file.
e.g. If one User opens the project from Project Server then Task A shows the
following (I believe correctly)
Forecast Date : 02/07/08
Critical?: No
Late Finish: 12/08/08
If another User opens the project (in eother read/write or read only mode)
then the following shows. I think this has to be incorrect anyway as the the
Critical indicator would be showing Yes if the late finish date was the same
as the forecast date?
Forecast date: 02/07/08
Critical?: No
Late Finish: 02/07/08
Can anyone explain why this happens?
We're using MS Project Server & MS Project Pro 2003