J
Jeff Ditty
Hello-
I am looking for a solution to the following problem:
I need to have a calculation in a column that generates the number of days a
project is off schedule. I currently have one baseline Start & Finish date
for each task, and one actual Start & Finish date for each task. What I
want to do is calculate the difference between the Baseline & Actual Start
Date, the Baseline & Actual Finish Date, and then add the two values
together to generate a value for how many days a task is off schedule. The
column would then keep a running sum of each task so that as you review the
latest task in the project, you can determine the current amount of days the
entire project is off schedule.
Anyone have any thoughts or solutions to this inquiry?
Thanks,
Jeff
I am looking for a solution to the following problem:
I need to have a calculation in a column that generates the number of days a
project is off schedule. I currently have one baseline Start & Finish date
for each task, and one actual Start & Finish date for each task. What I
want to do is calculate the difference between the Baseline & Actual Start
Date, the Baseline & Actual Finish Date, and then add the two values
together to generate a value for how many days a task is off schedule. The
column would then keep a running sum of each task so that as you review the
latest task in the project, you can determine the current amount of days the
entire project is off schedule.
Anyone have any thoughts or solutions to this inquiry?
Thanks,
Jeff