C
Capitol Mike
I'm using Project 2000 Standard
I would like to replace the "Work" cell in the Who Does What When report
with the "Project" cell.
I have the following selections:
Row: Resources
Column: 1 Days
Cell: Work
I need to change the cell to "Project", but the selections for the cell in a
crosstab report appear to be limilted to:
Actual Cost
Actual Overtime Work
Actual Work
ACWP
etc....
Why can't I choose the Project field to fill the cell?
Thanks in advance.
I would like to replace the "Work" cell in the Who Does What When report
with the "Project" cell.
I have the following selections:
Row: Resources
Column: 1 Days
Cell: Work
I need to change the cell to "Project", but the selections for the cell in a
crosstab report appear to be limilted to:
Actual Cost
Actual Overtime Work
Actual Work
ACWP
etc....
Why can't I choose the Project field to fill the cell?
Thanks in advance.