In Format>Gridlines, under the "Lines to change" list select "Status Date".
Set the line type and color. This will show the Status Date from
Project>Prject Information.
Thank you for that, it answered my question and now can show the date that my
schedule was updated to. I will have to remember to go into "project
information" each week to update that date.
Hi Ron,
You're welcome and thanks for the feedback.
Julie