Hello again. If I keep getting these problems I do not
know if I wish to use MS Project 2002 much longer.
However, I am trying to put a template together. My
standard work data are entered in minutes. However, MS
Project 2002 does not seem to do too good a job of
calculating these minutes in the Duration Section. If I
enter 5, 10, 20, 30 minutes in the work section the
duration is constantly listed as 0.88 days. Could anyone
tell me how to remedy this situation and have the work and
duration be consistent.
Also I have tried to access the FAQ for MS Project2002 and
some how have difficulty locating it. I click on the FAQ
Tab but have not seen anything that suggests FAQ.
Appreciate your assistance.
Q
know if I wish to use MS Project 2002 much longer.
However, I am trying to put a template together. My
standard work data are entered in minutes. However, MS
Project 2002 does not seem to do too good a job of
calculating these minutes in the Duration Section. If I
enter 5, 10, 20, 30 minutes in the work section the
duration is constantly listed as 0.88 days. Could anyone
tell me how to remedy this situation and have the work and
duration be consistent.
Also I have tried to access the FAQ for MS Project2002 and
some how have difficulty locating it. I click on the FAQ
Tab but have not seen anything that suggests FAQ.
Appreciate your assistance.