Default task dependancies (and lag days) for pairs of tasks

L

lornap

Dear all,

Can you create named/specific task dependancies such that when two tasks are
linked Project automatically set the lag days and type of dependancy based on
preprogrammed details?

Thanks,

Lorna.
 
J

John

lornap said:
Dear all,

Can you create named/specific task dependancies such that when two tasks are
linked Project automatically set the lag days and type of dependancy based on
preprogrammed details?

Thanks,

Lorna.

Lorna,
The default link type between tasks is Finish-to-start and I'm not aware
of any simple way to change that default. It might be possible to
develop an Event driven macro that automatically substitutes an
alternate pre-defined link type but that is probably more trouble than
it is worth.

John
Project MVP
 
S

Steve House [Project MVP]

You could possibly create a VB macro to do something like that but IMHO it
would be far more trouble than it would be worth to do it. A project plan
should not be such an automated rote exercise anyway. You, the manager,
still should be in charge of all the decisions as your plan goes from rough
draft to final work schedule. MSP is just there as a glorified calculator
to help you see the consequences of the choices you make but they always
need to remain YOUR choices as only you know what meets the required
objectives in the end. In the case of lag time, even if a certain pair of
tasks occurs repeatedly in your plan, for each iteration of A->B you should
be looking at it and asking yourself "Based on the conditions at the time we
doing them, what should the lag time between A and B be *this* time around?"
In most projects I would think it would rarely be the same for all
iterations of the tasks.
 