Hi, I have a series of linked tasks, say 101 to 105 with 1 day durations, and
I want to set the dependancies such that the last one finishes 2 days before
a separate milestone task, task 106. How do I do it so that task 1
automatically starts on the correct day, i.e. 7 days before 106. I don't
want to set 101 to start specifically 7 days before 106 as I want to be able
to change the durations for 101 to 105 and have the dates corrected
automatically.
Many thanks, Colin