T
Terry Montgomery
Greetings,
Ok, maybe I don't understand dependent tasks completely. Here's the deal. I
have a template project with tasks, start and finish dates, and durations
already set. I use this for a new project. I first set the Project Finish
date for the new project. No problem. Task #19 is "Receive Signed Contract".
It has no predecessor. It is a subtask of a Summary Task with a Start Date of
11/3/05.
I reset Task #19 as a Milestone with zero days. No problem. I then try and
reset the Start and Finish Date for the Milestone to 11/12/05. MS Project
refuses to let me reset the date. It maintains the Start and Finish Date the
same as the Summary Task Start Date of 11/3/05.
I try Task View and reset the date from there for the Milestone. It then
gives me an error message that the Milestone has a dependency on Task #117
which has a Start Date the same as the Summary Task of 11/3/05. Task #117 has
a predecessor of Task #14. I remove this predecessor from Task #117 even
though the Milestone is in a completely separate subtask group and has no
relationship to Task #14. MS Project still refuses to let me reset the
Milestone dates.
What gives?
Thanks,
Terry Montgomery
Ok, maybe I don't understand dependent tasks completely. Here's the deal. I
have a template project with tasks, start and finish dates, and durations
already set. I use this for a new project. I first set the Project Finish
date for the new project. No problem. Task #19 is "Receive Signed Contract".
It has no predecessor. It is a subtask of a Summary Task with a Start Date of
11/3/05.
I reset Task #19 as a Milestone with zero days. No problem. I then try and
reset the Start and Finish Date for the Milestone to 11/12/05. MS Project
refuses to let me reset the date. It maintains the Start and Finish Date the
same as the Summary Task Start Date of 11/3/05.
I try Task View and reset the date from there for the Milestone. It then
gives me an error message that the Milestone has a dependency on Task #117
which has a Start Date the same as the Summary Task of 11/3/05. Task #117 has
a predecessor of Task #14. I remove this predecessor from Task #117 even
though the Milestone is in a completely separate subtask group and has no
relationship to Task #14. MS Project still refuses to let me reset the
Milestone dates.
What gives?
Thanks,
Terry Montgomery