different works in a single day

T

Tat

A resource is assigned to work 8h/d.
In a day,he will work for 5hrs on one project and 3hrs on other project.
Using MSproj2007-Pro,In a single plan how can i show this?Is it necessary to
assign two different calendars of 5hrs and 3hrs to that resource....such that
5hrs calendar is assigned to the resource when planned for project and 3hrs
calendar when involved in other project?If not how to achieve this?
 
R

Reut

Hi
I dont think you need 2 different calendars. if you have those Project files
on server, you can open one of the files on Resource Usage View, and with the
AUTO FILTER on the "Project" column choose the projects you want to show
Hope i helped..Good Luck!!
 
M

Mike Glen

Hi Tat,

Welcome to this Microsoft Project newsgroup :)

You assign the resource to work on both tasks and then level.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 