Disable automatic calculation on % complete

R

Ris

How can I stop MS project from automatically changing the %c omplete when I
change the finish date on tasks. The system recalculates this if I change the
finish date, I want to stop this if possible.

Thanks
Ris
 
A

Alexander Barvinsky

Can you explain why it's not approach for you?
How can I stop MS project from automatically changing the %c omplete when I
change the finish date on tasks. The system recalculates this if I change the
finish date, I want to stop this if possible.

Thanks
Ris

Alerxander Barvinsky
Director of Operations Department
 
R

Ris

Were starting to use Project to track staff tasks and tasks are not always
going to be 50% complete when we are half way to the finish date. Sometines a
task can be completed 70% in the first week, so I need to be able to modify
the finish date without affecting the %complete
 
M

Mike Glen

Hi Ris,

Welcome to this Microsoft Project newsgroup :)

Project measures the %Complete based on the number of working periods
completed against the total number of working periods planned. The Duration
is just a measure of the working time between start and finish. Thus
Doration and %Complete are inextricably tied and you can't change one
without the other. (This, perhaps, is a good reason not to track staff
tasks within a project.) However, If you look at the % Work completed, it
could give you what want as it will remain correct irrespective of the end
date, provided the task is of Fixed Work type and changing the end date does
not introduce more or less work. That being said, it is not good practice
ever to insert start and finish dates as that is what Project is for - to
calculate the schedule for you. You enter the precedence link and the
Duration and Project will calculate the dates for you.

Another possibility is to create a hammock task that expands or contracts
with the controlling milestones - please see FAQ Item: 19. Hammock Tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 
R

Ris

Thank you Mike,

I will use the % Work Complete instead of the % Complete, this works.

THank you for your interest. :)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top