K
Kim
When I set the duration in Microsoft Project for say: two days, then the
start and finish date show three days,
for example if I set a duration of 2 days, start date 1/12/07 then finish
date in 3/12/07- I of course want a start date of 1/12/07 and finish 2/12/07
how do i rectify this??
Thanks
start and finish date show three days,
for example if I set a duration of 2 days, start date 1/12/07 then finish
date in 3/12/07- I of course want a start date of 1/12/07 and finish 2/12/07
how do i rectify this??
Thanks