M
Ms MIS
When a resource has been assigned to a task and they are then made
unavailable (non-working days) due to annual leave I am presented with the
following dialogue due to the conflict;
The resource is assigned outside the original dates for task "TASK NAME" in
project "PROJECT NAME".
The duration of this fixed-duration task will change to accommodate the
resource assignment.
I understand this is logically correct however it extends the task in
question and hence lengthens the entire project, rather than enabling a
manual resource replacement and maintaining the fixed-duration. Is there a
way to present this dialogue but not allow MSP to automatically change the
task to accommodate the resource assignment?
unavailable (non-working days) due to annual leave I am presented with the
following dialogue due to the conflict;
The resource is assigned outside the original dates for task "TASK NAME" in
project "PROJECT NAME".
The duration of this fixed-duration task will change to accommodate the
resource assignment.
I understand this is logically correct however it extends the task in
question and hence lengthens the entire project, rather than enabling a
manual resource replacement and maintaining the fixed-duration. Is there a
way to present this dialogue but not allow MSP to automatically change the
task to accommodate the resource assignment?