P
Peter Bons
Hi all,
i have a question about MS Project. I am not an expert in this tool, it's
one of our customers that has a problem with the total time of a project
being wrongly calculated.
The project lists 6 tasks with overlapping start en finishdates.
the durations of the seperate tasks are 1,1,1,1 and 2 days, yet the total
displays 4.94 days. What I do not understand is where the .94 comes from.
If I change the duration of one of the tasks from 1 till 2 days, the total
project time is calculated to 5 days.
My main question is, how to get rid of that .94 and make the total time a
whole number
Kind regards,
Peter Bons
i have a question about MS Project. I am not an expert in this tool, it's
one of our customers that has a problem with the total time of a project
being wrongly calculated.
The project lists 6 tasks with overlapping start en finishdates.
the durations of the seperate tasks are 1,1,1,1 and 2 days, yet the total
displays 4.94 days. What I do not understand is where the .94 comes from.
If I change the duration of one of the tasks from 1 till 2 days, the total
project time is calculated to 5 days.
My main question is, how to get rid of that .94 and make the total time a
whole number
Kind regards,
Peter Bons