T
Tat
Hi,
Does MS Project 2003 let you schedule the time based on the duration and
assign resources with effort time?
What I would like to achieve is to place a schedule for certain task for 2
days as duration. However, this task only takes about 10 hrs. and I would
like the resource assigned to be utilized 10 hrs instead of 16 hrs (full 2
day duration).
If I change the duration, to 10 hrs, then the project end time will shift
back causing the rest of the schedule to shift.
It sounds like a basic question, but any input is appreciated.
Tat
Does MS Project 2003 let you schedule the time based on the duration and
assign resources with effort time?
What I would like to achieve is to place a schedule for certain task for 2
days as duration. However, this task only takes about 10 hrs. and I would
like the resource assigned to be utilized 10 hrs instead of 16 hrs (full 2
day duration).
If I change the duration, to 10 hrs, then the project end time will shift
back causing the rest of the schedule to shift.
It sounds like a basic question, but any input is appreciated.
Tat