L
Laureen
Hello,
If a PM entered some of his duration as both days and some in hours- would
this have an impact on the finish variance (which does not seem to
calculating correctly). Also, for the tasks that were entered in hours, they
roll up to a Summary task that uses by day. The hours are to the minute,
like 13.76 (I doubt that the PM was that specific). Any ideas as to what
might be happening here?
Thanks in advance.
If a PM entered some of his duration as both days and some in hours- would
this have an impact on the finish variance (which does not seem to
calculating correctly). Also, for the tasks that were entered in hours, they
roll up to a Summary task that uses by day. The hours are to the minute,
like 13.76 (I doubt that the PM was that specific). Any ideas as to what
might be happening here?
Thanks in advance.