Durations

F

flipflop

I have a project that originally used the standard calendar. It has a start
date of 04/24/07, an end date of 04/25/08 and a total duration of 264 days.
If I change to the 24 hour calendar the end date changes to 07/21/07, but the
duration stays at 264 days. Why doesn't the duration of each task decrease
with the change in the calendar?
 
J

JulieS

Hi flipflop,

The schedule of your tasks changed because you are now working with a
calendar which allows 24 hours of work per day. However, the definition of a
"day" that is being used in the duration field is still 8 hours.

See FAQ #5 at http://project.mvps.org/faqs.htm

I hope this helps. Let us know how you get along.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top