flipflop
I have a project that originally used the standard calendar. It has a start
date of 04/24/07, an end date of 04/25/08 and a total duration of 264 days.
If I change to the 24 hour calendar the end date changes to 07/21/07, but the
duration stays at 264 days. Why doesn't the duration of each task decrease
with the change in the calendar?
date of 04/24/07, an end date of 04/25/08 and a total duration of 264 days.
If I change to the 24 hour calendar the end date changes to 07/21/07, but the
duration stays at 264 days. Why doesn't the duration of each task decrease
with the change in the calendar?