Paul said:
John,
No time machine. (although if you find one, let me know, I have some stocks
I'd like to go back and invest in) But every task has an expected completion
date and a duration. I would think there would be a way to convert that info
into a reasonable schedule. It sounds like I need to export into Excel, but
once I get it there, then what? Whatever I do has to be repeatable. My boss
will want one twice a week.
Paul
Paul,
Well, what you describe is the classic building block of a schedule
plan. Each task that is required to complete the plan has a start date
and estimated duration. The start date may be independent of other tasks
or dependent. In the latter case, tasks are logically linked to show the
flow of task progression. Project then takes the start dates, estimated
duration and intertask linkages and creates a schedule. So it sounds
like you have the elements of a schedule. What I'm having trouble
understanding is the concept of future % complete. In Project, %
complete is used to describe what has happened as of some point in time
with respect to working the original plan. Therefore, % complete values
are only available through that point in time, usually referred to as
the Status Date. "Future" % complete is speculative.
Now either I don't understand what you are after or you are asking for
something that isn't available. Jack supplied a couple of methods for
exporting data to Excel where it can be plotted, but again, that plot
will only describe performance through the Status Date.
Still confused.
John
Project MVP