Hi,

I want to edit the formula for Actual Cost field in Microsoft Project
2003.

Is it possible to do so???

Also, I wish to know whether I can assign different currency for each
resources... ?

For Ex: Resource1 : INR
Resource2: USD

Plz help me..

Thanx
 
J

Jan De Messemaeker

Hi,

In Tools, Options, Calculation, check out "Actual Costs are always
calculated by Microsoft Project"
Multiple currencies, I don't think so, sorry :-(
 
S

Sobin

Hi Jan,

Thanx for response.

But How can I edit the formula to include another custom field?

Thanx
 
J

Jan De Messemaeker

Hi,

Sorry to have misinterpreted the word Edit.
YOu can program any formyula in a VBA macro angd that one can write in teh
Actual Cost field, provided you don't let Project calculate the Actal cost.
HTH
 