A
april
I'm confused about the difference between the two. The microsoft help file has the following definition:
- Entered field is a field in which you may type or edit information
- calculated field is a field in which the value is determined by the Project base don other fields. Project may recalculate the value automaically or when you specif
Are start and end date entered fields or calculated fields? if I have two tasks a and b with FS dependency, does that make the dates for task b calculated fields?
The reason I'm asking is because I'm having problems importing project data from another file format. The help file suggests that only information in "entered field" can be imported. I created a project and specified a project start date. The imported file (in xml format) is identical to this project, with only difference being that all planned dates (starting from the project start date) were shifted by 3 days. All task durations and dependencies were preserved. When importing the file and merging it with the existing project, isntead of getting the updated project plan, I ran into conflicts with sub-tasks and none of dates for the sub-tasks were moved as a result. I don't understand how this would happen, even if project ignored all other date fields in the import file and used only project start date during the import/merge, the calculated task dates should be the same as what I had in my import file?
- Entered field is a field in which you may type or edit information
- calculated field is a field in which the value is determined by the Project base don other fields. Project may recalculate the value automaically or when you specif
Are start and end date entered fields or calculated fields? if I have two tasks a and b with FS dependency, does that make the dates for task b calculated fields?
The reason I'm asking is because I'm having problems importing project data from another file format. The help file suggests that only information in "entered field" can be imported. I created a project and specified a project start date. The imported file (in xml format) is identical to this project, with only difference being that all planned dates (starting from the project start date) were shifted by 3 days. All task durations and dependencies were preserved. When importing the file and merging it with the existing project, isntead of getting the updated project plan, I ran into conflicts with sub-tasks and none of dates for the sub-tasks were moved as a result. I don't understand how this would happen, even if project ignored all other date fields in the import file and used only project start date during the import/merge, the calculated task dates should be the same as what I had in my import file?