S
Saviz
Hi,
Scenario : I am working on a schedule with several hundred tasks, Just need
advice on how to update the Start/Finish date. I have read that changing the
these dates manually is not a good approach...
However what should I do if I simply would like to change a start date for a
task?
In general what is the best approach when it comes to updating start/finish
dates?
Many Thanks
Scenario : I am working on a schedule with several hundred tasks, Just need
advice on how to update the Start/Finish date. I have read that changing the
these dates manually is not a good approach...
However what should I do if I simply would like to change a start date for a
task?
In general what is the best approach when it comes to updating start/finish
dates?
Many Thanks