J
Jeff L.
If I assign resources from the Build Team From Enterprise
window, can I still define the resource with a Max Units
of 40% in the individual project Resource Sheet and have
that take precedence? If so, and I have the resource
assigned to 2 projects, one at 40% Max Units and the other
at 50% Max Units, will the Enterprise Resource Pool still
show this resource as having 10% remaining availability?
window, can I still define the resource with a Max Units
of 40% in the individual project Resource Sheet and have
that take precedence? If so, and I have the resource
assigned to 2 projects, one at 40% Max Units and the other
at 50% Max Units, will the Enterprise Resource Pool still
show this resource as having 10% remaining availability?