Estimate at Completion / Variance at Completion

T

toast88

All,

My project plan's summary tasks are not rolling up the EAC/VAC values
for the non summary tasks correctly. The values are correct for the non
summary tasks below the summary tasks. Anyone experience this and know how to
fix?

Thanks!
 
J

Jim Aksel

Although I have not had this specific experience, I had a similar one with
BCWP. What I found was that not all my tasks were using the same EV method.
Also, Tools/Optoins/Calculations/Earned Value... needs to be set.

Start there.

It might also be as simple as hitting the F9 key to recalculate.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top