M
marie
Hi there,
Is there a way to track Actual Dates independent of the planned/expected
Dates? The dates of the tasks on our project changes all the time, so what we
did was to add columns to track the (planned/expected) Start and Finish dates
versus the Actual Start and Finish dates. What we found is that whenever we
change the Actual date, the planned/expected date changes as well i.e. the
planned/expected date copies the date indicated as the actual date.
What we want MS Project to show are different dates for expected and
actuals.
Is there a way of doing this?
We are using MS Project 2003 standard (Win XP).
Thanks for your help.
Is there a way to track Actual Dates independent of the planned/expected
Dates? The dates of the tasks on our project changes all the time, so what we
did was to add columns to track the (planned/expected) Start and Finish dates
versus the Actual Start and Finish dates. What we found is that whenever we
change the Actual date, the planned/expected date changes as well i.e. the
planned/expected date copies the date indicated as the actual date.
What we want MS Project to show are different dates for expected and
actuals.
Is there a way of doing this?
We are using MS Project 2003 standard (Win XP).
Thanks for your help.