Export Unassigned task list to excel

C

CB

Is there a simple way to export the unassigned task for a project to excel?
I am using 2007 standard and only need to export task for a single project
that have no resource assignment. I would like to include the duration and
start and finish fields. Any ideas greatly appreciated.
 
R

Rod Gill

Hi,

Try creating a filter that shows all tasks with Resource Names=Blank then
File, Save as and select Excel .xls format. A wizard will then start and you
can select which fields you want exported by creating your own map.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 