D
Dave
I have a project with 1000+ tasks with a myriad of dependencies.
What I want to do is to isolate 1 task and display all predecessor and
successor tasks related to this 1 task and view it in a Gantt chart. I only
want to see that 1 task and any other tasks dependant on that 1 task.
Basically I want to isolate 1 branch from my project.
I was wondering if there is some way I can do this with a filter?
The other way I was thinking was maybe if I made this task the critical path
somehow I could isolate it this way. So far I can't figure out how to do
this without changing the dates.
Any ideas?
Thanks
What I want to do is to isolate 1 task and display all predecessor and
successor tasks related to this 1 task and view it in a Gantt chart. I only
want to see that 1 task and any other tasks dependant on that 1 task.
Basically I want to isolate 1 branch from my project.
I was wondering if there is some way I can do this with a filter?
The other way I was thinking was maybe if I made this task the critical path
somehow I could isolate it this way. So far I can't figure out how to do
this without changing the dates.
Any ideas?
Thanks