ChuckB
I manage large projects with numerous tasks that have multiple resource
assignments. Lately, I have discovered a number of cases where resources
actual work is quite a bit more than the baseline amount. I have created a
flag that will
tell me when the actual work for the task as a whole exceeds baseline but am
unable to devise a method to tell when a resource is over baseline but the
task
itself is not. Example: Task total work is 80 hours divided evenly among
two resources--40 hrs each; one resource has no actual work and the other has
actual of 60 hours, which is over baseline yet the task as a whole is not
over. I would like to be able to create a report or flag to spot that
resource.
assignments. Lately, I have discovered a number of cases where resources
actual work is quite a bit more than the baseline amount. I have created a
flag that will
tell me when the actual work for the task as a whole exceeds baseline but am
unable to devise a method to tell when a resource is over baseline but the
task
itself is not. Example: Task total work is 80 hours divided evenly among
two resources--40 hrs each; one resource has no actual work and the other has
actual of 60 hours, which is over baseline yet the task as a whole is not
over. I would like to be able to create a report or flag to spot that
resource.