Rhammia Immanuel
Hi!
Would appreciate any help in this area.
I have a task B that has already started with the below Start and Finish
dates. Its a Fixed work task.
Task B Start 05/05/06 Finish 07/28/06
I also have Task A that has also started and the dates are below.
Task A Start 05/05/06 Finish 08/16/06
I make TaskA as Predecessor to Task B with a Finish to Finish with 10 days
lag.
I was hoping for the Finish date for Task B to change to something like
08/31/06 - 10 days after 08/16/06. Task B still has 07/28/06 as the Finish
Date.
I expected the duration to change as it is Fixed hours and the units to
decrease.
I am on Project 2000.
Please tell me why this is not happening.
Thanks
Immanuel
Would appreciate any help in this area.
I have a task B that has already started with the below Start and Finish
dates. Its a Fixed work task.
Task B Start 05/05/06 Finish 07/28/06
I also have Task A that has also started and the dates are below.
Task A Start 05/05/06 Finish 08/16/06
I make TaskA as Predecessor to Task B with a Finish to Finish with 10 days
lag.
I was hoping for the Finish date for Task B to change to something like
08/31/06 - 10 days after 08/16/06. Task B still has 07/28/06 as the Finish
Date.
I expected the duration to change as it is Fixed hours and the units to
decrease.
I am on Project 2000.
Please tell me why this is not happening.
Thanks
Immanuel