Mary Ann
I have a fixed duration task with a resource assigned to it. In the resource
calendar I have marked individual non-working time.
When I allocate the resource to the task, sometimes Project schedules the
task and ignores the resource holiday, which results in the task taking place
on a day when the resource is not available.
At other times, Project displays a message indicating that it is going to
increase the task duration. It then extends the task to include a date when
the resource is available.
What controls which route Project takes? How do I control this?
calendar I have marked individual non-working time.
When I allocate the resource to the task, sometimes Project schedules the
task and ignores the resource holiday, which results in the task taking place
on a day when the resource is not available.
At other times, Project displays a message indicating that it is going to
increase the task duration. It then extends the task to include a date when
the resource is available.
What controls which route Project takes? How do I control this?