A
AM
Hey;
We are traking progress against % completes. So we decided to add a
column which would have Forecast % complete to the plan. This would
show us the deltas each week as to what was forecasted and where they
actually are (% complete).
But I realized there is no Forecast% complete in MS Project. Would
anyone help me how I could do this. Is there a way? Please advice.
Thanks
AM
We are traking progress against % completes. So we decided to add a
column which would have Forecast % complete to the plan. This would
show us the deltas each week as to what was forecasted and where they
actually are (% complete).
But I realized there is no Forecast% complete in MS Project. Would
anyone help me how I could do this. Is there a way? Please advice.
Thanks
AM