T
Thunderchicken95
Hello everyone! OK, I'll explain it like this. I schedule work for an
offshore platform. The biggest constraint is "POB" (people on board). Alot of
the Tasks require additional POB. I use MSP in a group meeting to show the
schedule "ghant chart" and we like to shuffle the tasks around to optimize
POB. Maoving the tasks around is a breeze. However showing what it does to
the POB is a different story. I have been using an excel graph to show the
total POB on a given day. Because this is "static" when I move tasks around
in Project everything is out sync and we all get confused. Any Ideas? Thanks
in advance!
offshore platform. The biggest constraint is "POB" (people on board). Alot of
the Tasks require additional POB. I use MSP in a group meeting to show the
schedule "ghant chart" and we like to shuffle the tasks around to optimize
POB. Maoving the tasks around is a breeze. However showing what it does to
the POB is a different story. I have been using an excel graph to show the
total POB on a given day. Because this is "static" when I move tasks around
in Project everything is out sync and we all get confused. Any Ideas? Thanks
in advance!