gantt bar not showing bar for % complete

J

jackie

Hello

Please let me know how to get the line for the % complete showing on the
gantt bar. If I click to format the bar I get the formatting options for the
whole bar and not just the % complete

Many thanks
J
 
A

Andrew

Jackie

Go to Format Bar styles and add a bar for progress make it look like you
want it to, and then in the from and to section have the bar going from
actual start to complete through. I normally have the progress bar filling in
the top half with the % at the right hand side of the progress bar not the
baseline so it is easier to read

hope this helps.

Andrew
 