R
Robin Roe
Hi,
I have come across a number of schedules where the % complete (default black
progress line on the bar) does not end exactly at the status line. Is this
possible considering the default % complete is % duration complete? I would
agree that the % work complete or the physical % complete may not match the
status line, but can this be true of the % duration complete?
Example
A task of 5 days duration started on Monday 1st , the status date is set to
Tuesday 2nd, the task has to be 40% complete and will match the status line.
It physically can’t be anything else, can it? If it’s decided the task will
now take 10 days instead, the task has to be 20% complete. (2 days out of 10
is 20%).
Do people agree/disagree with this? The way I look at it is that everything
to the left of the status line is complete and everything to the right is yet
to be done. Am I correct in my assumption?
Thanks
I have come across a number of schedules where the % complete (default black
progress line on the bar) does not end exactly at the status line. Is this
possible considering the default % complete is % duration complete? I would
agree that the % work complete or the physical % complete may not match the
status line, but can this be true of the % duration complete?
Example
A task of 5 days duration started on Monday 1st , the status date is set to
Tuesday 2nd, the task has to be 40% complete and will match the status line.
It physically can’t be anything else, can it? If it’s decided the task will
now take 10 days instead, the task has to be 20% complete. (2 days out of 10
is 20%).
Do people agree/disagree with this? The way I look at it is that everything
to the left of the status line is complete and everything to the right is yet
to be done. Am I correct in my assumption?
Thanks