C
CK_PMP
Good morning! Two part question:
1) I'm using the report generator ("View" -> "Report") to create a task
usage (work) report. However, I can't get recurring tasks to display their
work in the "totals" column. The only way to get it to show is to expand the
task; I'd really like to have all of the recurring tasks collapsed when I
generate the report. Is this possible?
2) Ideally what I'd REALLY like is a report that just shows resource
utilization by time unit (e.g., week, month, etc), but DOES NOT show
individual tasks or resources. Basically, I'm just trying to plot, over
time, how many FTEs are needed to perform the work required by ALL tasks. I
don't care if it's a line graph or bar graph.
And if anyone's feeling particularly helpful/smart this morning: is there
any way to combine/merge tasks? For example, Task 1 is called: "Bake Pie"
and Task 2 is called "Taste Pie." The resources are the same, but
utilization is much lower for Task 2. There is another task in between that
is done externally to the project (let's call it "Remove Pie From Oven"), so
my resources perform work, wait a given period of time, and then perform some
follow-up work. Currently I have them as two tasks, with a FS+edays
dependency. Is it possible to merge these non-consecutive tasks? Would I
even want to? Or would I be better off leaving them as-is? My motivation
for merging is just for simplicity (simpler reports, fewer tasks to deal
with). Thanks!
1) I'm using the report generator ("View" -> "Report") to create a task
usage (work) report. However, I can't get recurring tasks to display their
work in the "totals" column. The only way to get it to show is to expand the
task; I'd really like to have all of the recurring tasks collapsed when I
generate the report. Is this possible?
2) Ideally what I'd REALLY like is a report that just shows resource
utilization by time unit (e.g., week, month, etc), but DOES NOT show
individual tasks or resources. Basically, I'm just trying to plot, over
time, how many FTEs are needed to perform the work required by ALL tasks. I
don't care if it's a line graph or bar graph.
And if anyone's feeling particularly helpful/smart this morning: is there
any way to combine/merge tasks? For example, Task 1 is called: "Bake Pie"
and Task 2 is called "Taste Pie." The resources are the same, but
utilization is much lower for Task 2. There is another task in between that
is done externally to the project (let's call it "Remove Pie From Oven"), so
my resources perform work, wait a given period of time, and then perform some
follow-up work. Currently I have them as two tasks, with a FS+edays
dependency. Is it possible to merge these non-consecutive tasks? Would I
even want to? Or would I be better off leaving them as-is? My motivation
for merging is just for simplicity (simpler reports, fewer tasks to deal
with). Thanks!