Rich-CFS said:
Is there a way to establish and name a set of milestones so the set can be
assigned to multiple tasks throughout my Gant chart to avoid cutting and
pasting?
Rich-CFS,
Perhaps there's a difference in terminology here but milestones
shouldn't be "assigned" to tasks. A milestone should be a zero duration
entry that marks the start and/or completion of a major group of tasks
within a project plan. Milestones have no resources assigned and
milestones incur no cost, although completion of a milestone may trigger
a progress payment, or something similar.
Unless you are creating a large file that depicts several independent
separate projects, there should only be a few milestones and there is no
reason to repeat any given milestone. Once the group of tasks preceding
the milestone is completed, that milestone is complete, never to be
repeated again.
With regard to setting up a group of milestones. Some users like to
gather all plan milestones under a single summary line at the top of the
plan so its easier to see the overall progress of a plan at a glance.
But that's about the extent of creating a set of milestones.
John
Project MVP