Hi - I am a new user and am scheduling a small project. At this time, I have
not added resources (people), but instead am trying to create the schedule
based on available working hours per day as I have assigned in the project
calendar (to 19 hours per day, that will be spread accross 3 engineers). For
some reason, the project is scheduling every task to begin on the same day
with no regard to the 19 hour contraint. The duration of my project has
defaulted to the duration of the longest task - so it's super compressed.
There are not dependencies between the tasks. Can anyone help?
Thank you.
not added resources (people), but instead am trying to create the schedule
based on available working hours per day as I have assigned in the project
calendar (to 19 hours per day, that will be spread accross 3 engineers). For
some reason, the project is scheduling every task to begin on the same day
with no regard to the 19 hour contraint. The duration of my project has
defaulted to the duration of the longest task - so it's super compressed.
There are not dependencies between the tasks. Can anyone help?