Help ! -- Getting Percent Complete statistics in MS Project

L

Lang

A question on MS Project. If you open a project, open project information
dialog and then click statistics button at the bottom, you will see the
Percent Complete info, which includes both duration percent and work percent.
Question:

- How to obtain such information for each developer?

- How to obtain such information for each top level task?


I have spent lots of time on this and still couldn’t figure it
out. I want to get statistics for each developer on how they are doing on a
project. For example, I can divide the work percent by duration percent, then
I could tell how much(in percentage) a developer is ahead or behind of
schedule.

Thanks for the help in advanace,
Lang
 