N
Neil Greene
My company has work which is planned in project, that is tied into our time
and billing system. In this particular situation, I have tasks which have
unknown hours, but known duration. Say, TASK A will last from Jan 1-Dec 31.
I want this tasks duration to be 1 year, and I want to allocate or buget N
number of hours for a particular resource.
I have created a calendar for the resource assignments which defines a day
as 24 hours, and 365 days a year. So, work can be conducted at any time of
the year. I want the task duration to ALWAYS START/END Jan 1 - Dec 31, or
some defined duration.
What is the best way to define the project and/or tasks?
and billing system. In this particular situation, I have tasks which have
unknown hours, but known duration. Say, TASK A will last from Jan 1-Dec 31.
I want this tasks duration to be 1 year, and I want to allocate or buget N
number of hours for a particular resource.
I have created a calendar for the resource assignments which defines a day
as 24 hours, and 365 days a year. So, work can be conducted at any time of
the year. I want the task duration to ALWAYS START/END Jan 1 - Dec 31, or
some defined duration.
What is the best way to define the project and/or tasks?